QUICK LINKS
Fulton Street Transit Center
Begun after the tragedy of September 11th, the Fulton Street Transit Center was designed to be a grand transit station in the heart of Lower Manhattan. The facility is to connect 12 subway lines and make room for 23,000 square feet of retail space within a soaring glass dome. In addition, it will help make the individual stations and trains served by the center less congested, as well as make their connections less circuitous and more accessible to those with disabilities. The project received $750 million of the $20 billion that was pledged towards the recovery of Lower Manhattan by the Federal Government. In order to proceed, numerous properties were acquired by the MTA and 145 businesses were displaced, some by eminent domain.
The current budget for the project, however, is now over $900 million, reflecting an increase in construction costs as well as increased costs to acquire the necessary real estate. In addition, the scheduled completion of the project has been pushed back several times, and is now uncertain. Several of the underground portions of the project are near completion and the MTA requested bids for the last several pieces of the project in 2007, including the glass dome and the remaining underground work. However, when bids were due in early 2008, only one bid was received, which was more than double what the agency had anticipated. The MTA rejected the bid, and MTA CEO Lee Sander ordered a review of the project to identify where the budget could be scaled back and how the MTA could contain costs. Likely outcomes of this re-evaluation include an issuance of several RFP’s that break the remaining tasks into smaller projects as well as scaling back of the grand design plans for the above ground station building.
However, many in Lower Manhattan are not happy with discussions of scaling back the Fulton Street station. Groups such as the Alliance for Downtown New York and Manhattan’s Community Board 1 are urging the MTA to fulfill its promise to deliver a world class transit center to Lower Manhattan. They claim that the region needs the facility in order to remain economically competitive. In addition, many believe that the MTA needs to build a grand transit center since that was the promise made to Lower Manhattan, which has had to deal with several years of construction impacts, a large vacant plot of land, and several condemnations. For his part, Sander has stated that the MTA is committed to the Fulton Street center and that stopping work on the project is not an option. While plans may have to be scaled back or slightly delayed, Sander has stated that he is not in favor of stopping work on the project.
Potential Changes May Be Made to World Trade Transit Hub
Wednesday, August 27, 2008 | New York Times | Topic: Transportation
In a project that has been going over costs, some changes may be made to the interior of the new transit hub at the World Trade Center in order to lower costs. Since the original design featured a large expanse with no support beams some are proposing other alternatives which may be less labor intensive and therefore cheaper to complete in a timely fashion.
MTA Commits to ‘Elegant’ Entrance for Fulton St Transit Hub
Sunday, August 03, 2008 | New York Daily News | Topic: Transportation
The MTA’s Capital Construction Co. President Michael Horodniceanu announced that the MTA would deliver on its commitment to build an ‘elegant’ entrance for the Fulton Street Transit Hub. Horodniceanu noted that the plans might change somewhat, but that the defining features of the original designs, like an above-ground structure providing natural light into the transit mezzanine and ample retail, would be included in the new designs. The current budget for the transit hub is $1.2 billion, of which the MTA has secured about 900 million mostly federally funded dollars. As of yet, no completion date has been set for the project.
MTA Defends Work at Fulton Street Transit Hub
Thursday, April 10, 2008 | NY1 | Topic: Transportation
The Metropolitan Transportation Authority (MTA) said that progress is being made on work underground at the Fulton Transit Center and has recently decided to break up the plans in order to complete the transit hub. At a City Council hearing, the MTA acknowledged the idea of relocating a performing arts center above the transit center. The MTA hinted that they would like to keep the original design as intact as possible. However, new plans for the transit hub are expected in the next month or so from the MTA and then work must be done to figure out how to cover the budget shortfalls.
Schick Proposes New Location for WTC Performing Arts Center
Thursday, April 10, 2008 | New York Times | Topic: General
Avi Schick, the chief executive of the Empire State Development Corporation and chairman of the Lower Manhattan Development Corporation, has suggested a new plan for the location of the performing arts center intended for the World Trade Center site. Schick has recommended that the center be constructed on top of the Fulton Street subway station, suggesting that the change would cut costs and time. Schick’s proposal would be a departure from the previous plan to have retail above the station. The City’s cultural affairs commissioner, Kate Levin, has told the State that they will review the plans and respond within 30 days. Opponents of Schick’s plan worry that changing the plans may cause further delays in development of the transit center. There are also concerns about the noise and vibrations from the transit center disrupting performances.
Former WTC Area Business Owners Want Payments From MTA
Thursday, April 10, 2008 | Metro New York | Topic: General
Many business owners who were forced out of their properties near the World Trade Center site to make way for the Fulton Street Transit Center are frustrated with the treatment they have received from the Metropolitan Transportation Authority (MTA). The business owners’ properties were seized via eminent domain hearings about two years ago and they were promised relocation settlements; according to an MTA spokesperson, 25 business owners have yet to be paid. The plans for the glass-domed station have now been all but scrapped due to lack of funding and the site may become just an open plaza.
$20 Billion in Development At Risk Due to Slowing Economy
Monday, March 31, 2008 | New York Daily News | Topic: Economic Development
Due to the slowing economy, over $20 billion in development projects in the City could be scaled back, significantly delayed or even killed. The affected projects include Moynihan Station, Fulton Station, Atlantic Yards, Coney Island and the World Trade Center redevelopment. According to Robert Yaro, president of the Regional Plan Association, “We’re not going to throw in the towel on any of these projects, but less dramatic and less expensive designs may be needed.”
MTA Assures Something Will Be Built at Fulton Station
Friday, March 07, 2008 | Downtown Express | Topic: General
The Metropolitan Transportation Authority (MTA) hinted that some sort of building will arise at the Fulton Street Transit Hub, although it remains unclear what that building will look like. Local officials and displaced business owners are distrusting of the MTA’s promises that something will be built. The MTA has assured those involved that work progresses on the underground improvements needed at Fulton. The MTA has said the new outdoor structure will be more than just a plaza but will not be the original design planned.
MTA Prepares New Capital Plan; Project Delays Persist
Wednesday, February 27, 2008 | Reuters US Edition | Topic: Transportation
Rising construction costs and $9 billion gap in the MTA’s capital plan are causing delays in several capital projects, including the 2nd Avenue subway line, the East Side Access project, and the Fulton Street Transit Center. In response, the agency has drafted a new capital plan that includes $4.5 million in bonds from the proposed congestion pricing plan and will expand the budget from $21.3 to $29.5 billion.
MTA Projects Over Budget and Behind Schedule
Wednesday, February 27, 2008 | NY1 | Topic: Transportation
Because of rising construction costs, the Metropolitan Transportation Authority (MTA) will be $1.5 billion over budget in its four big construction projects: the 2nd Avenue Subway, East Side Access, the Fulton Street Transit Center and rebuilding the South Ferry terminal. Because of the budget problems, both the 2nd Ave. Subway and the East Side Access project have been delayed. They were both scheduled to open in 2013, but MTA now projects that they will open in 2015. Although the MTA’s five-year capital rebuilding program, which includes all these projects, may be cut back, the MTA does expect to pass the current plan along to legislators.
Community Board 1 Wants Original Plans for Fulton Station
Tuesday, February 12, 2008 | Metro New York | Topic: Transportation
At a meeting yesterday with Community Board 1 and the Metropolitan Transportation Authority (MTA), members of the board told the MTA to continue with its original plans for the Fulton Street Station. The board cited the use of eminent domain on roughly 145 businesses and the inconvenience that the residents of downtown Manhattan have had to deal with during the construction period as reason to continue to forward with the project. The Downtown Alliance is asking the MTA to consider a public/private partnership to get the project done if the MTA can not complete it on its own.
Public Plaza A Possibility for Fulton Transit Center
Thursday, January 31, 2008 | WNYC | Topic: Land Use
The Metropolitan Transportation Authority (MTA) is considering its options for the above ground area surrounding the Fulton Street Transit Center including a public plaza or park. The MTA is also considering selling its air rights over the transit center. This could be problematic since the land was acquired through eminent domain. The MTA will use the next month to evaluate the station plans and lower the estimated costs. Officials have continued to assure the public that underground work will precede as initially planned.
MTA Spent $25 Million On Fulton Plans
Wednesday, January 30, 2008 | New York Post | Topic: Transportation
The Metropolitan Transportation Authority (MTA) announced that it can only afford to complete the underground portion of the Fulton Street Transit Center. The transit hub is expected to be completed in 2010 at a cost of $930 million. The MTA had previously spent $25 million for the designs of a grand pavilion above ground which they no longer can afford to build, and will spend the next month trying to determine what they can afford to build in its place. Assembly Speaker Sheldon Silver blamed the agency for failing to deliver on its promises.
Displaced Fulton Center Business Owners Feel Slighted by MTA
Tuesday, January 29, 2008 | Newsday.com | Topic: Transportation
Yesterday the Metropolitan Transportation Authority (MTA) announced that once again it is scaling back efforts to build a new state-of-the-art transit center downtown. While the MTA says that they would have needed to acquire all of the businesses regardless if they built a grand entranceway, which was part of the plan that got scrapped yesterday, some business owners are left speculating if they were moved unnecessarily. In a separate debate, some business owners who were relocated by the MTA through eminent domain are demanding greater compensation for the value of their stores and the cost of moving. The MTA is currently negotiating with these business owners.
MTA Reevaluates Fulton Street Transit Center Plans
Monday, January 28, 2008 | New York Sun | Topic: Urban Design & Architecture
After cost overruns and major construction delays, MTA will reevaluate its plans for the Fulton Street Transit Center. The Transit Center, which will connect 12 subway lines, was originally expected to be completed in 2007 but that has been pushed back to late 2009. Potential new plans might scale down design elements of the proposed large domed shopping center, and build a more modest “public plaza.”
Further Delays for Fulton Transit Center
Wednesday, January 16, 2008 | New York Daily News | Topic: Land Use
The expected completion date of the Fulton Transit Center has been pushed back again, to as late as 2010. The Metropolitan Transportation Authority (MTA) rejected the only bid on the project because it was too overbudget. It is now planning to divide the contract into several projects to draw several bidders and reduce costs. The original plans are also being scaled down. The president of the MTA’s Capital Construction Co. will present a plan of action to MTA board members this month.
MTA Capital Construction President Resigns
Wednesday, January 09, 2008 | New York Daily News | Topic: General
Mysore Nagaraja, president of the Metropolitan Transportation Authority’s Capital Construction Co., is leaving at the end of January to take a consultant position in the private sector. His projects included the LIRR extension to Grand Central Terminal, the Second Avenue subway, the Fulton St. Transit Center and the No. 7 train extension. MTA officials express concern about how Nagaraja's departure will affect delays and rising costs for these projects.
Traffic Flows Considered for Lower Manhattan
Monday, March 12, 2007 | New York Sun | Topic: Transportation
Anticipating summer congestion in Lower Manhattan due to the construction of the Fulton Street Transportation Center, the city's Department of Transportation is considering plans to limit automobile traffic south of Ann Street on Broadway to city buses. Alternatively, the city is considering how to speed bus traffic on Broadway south of Houston by constructing five "bus bulbs," which are stretches of extended sidewalk space that reduce the time that it takes for buses to re-enter traffic. The plans to reduce traffic congestion by closing parts of Broadway to vehicle traffic will be overseen by Downtown Alliance, the manager of Lower Manhattan's Business Improvement District, Manhattan's Community Board 1, and City Council Member Alan Gerson. No specific time-line exists for the approval process.
Lower Manhattan Office Market in Healthy Recovery
Sunday, February 25, 2007 | Newsday.com | Topic: Economic Development
After hitting a vacancy rate of 17% in 2002, the downtown Manhattan office market has rebounded, with current vacancy rates finally down to pre-Sept 11th levels. Rents have also been increasing and there seems to be healthy demand for the large portion of new office space under construction in the Freedom Tower and new World Trade Center towers. Developers believe that the downtown market has benefited from relatively cheaper rates as compared to midtown, the creation of new housing in downtown which makes it a convenient commuting location for employees, and the recent large investment in public transportation and transit hubs.
Spitzer Approves Freedom Tower Plan
Tuesday, February 20, 2007 | Crain's New York Business | Topic: Politics & Government
Governor Spitzer today approved construction plans for the World Trade Center Freedom Tower. The governor had previously been against construction of the tower because of his concerns about whether or not it was economically viable. With a pickup in the downtown real estate market, he appears to have changed his mind. Spitzer stated that he believes there is a good chance the project can be completed within its current budget, and the Port Authority has continued to look at potential private investors for funding. The tower as well as the Sept. 11th memorial Fulton Street transit hub had previously been delayed because of budget concerns and had undergone several design changes.
Grand Central Seen as Inspiration for Fulton Street
Thursday, February 01, 2007 | New York Daily News | Topic: Transportation
The MTA is hoping to make Fulton Street Transit Center a new landmark worthy of visiting. The transit center has 24,000 square feet of commercial space, and the MTA has said that it will look at the organization and success of Grand Central Terminal as its model in filling these commercial leases. Overall the project is an attempt to ease transfers during commuting and create a more inviting and less confusing public space and transportation system in Lower Manhattan.
Charles Maikesh, Overseeing the Lower Manhattan Construction Tangle
Thursday, February 01, 2007 | New York Sun | Topic: Economic Development
Mr. Maikesh, Executive Director of the Lower Manhattan Command Center, is overseeing a huge revitalization and reconstruction of the neighborhood. The organization coordinates the construction of the World Trade Center and at least fifty-eight other construction projects in Lower Manhattan. Mr. Maikesh has worked with the Port Authority for many years and was originally in charge of repairing the World Trade Center after the 1993 bombings. While Mr. Maikesh admits that there are years of work ahead, he hopes successfully manage the process, allowing the West Side Highway, the Fulton Street Transit Center, and much of the work on the World Trade Center to be completed within the next five years.
MTA Will Avoid Cutting any Major Projects Despite Cost Overruns
Wednesday, January 31, 2007 | AM New York | Topic: Transportation
While concerns of large cost overruns among the MTA’s many construction projects have some worried about the continuation of funding on some of the agency’s projects, the MTA has stated that it does not plan to cut any major projects. A panel has been organized to review the timing and costs of all major projects and attempt to find areas in which costs can be cut. They will be reporting results of their review in sixty to ninety days, and may become a permanent watchdog panel within the MTA.
Final Design of Fulton Street Transit Center Unveiled
Tuesday, January 30, 2007 | Metro New York | Topic: Transportation
The Metropolitan Transportation Authority (MTA) has revealed final plans for the Fulton Street Transit Center in Downtown Manhattan. The design calls for a public main building with 24,000 square feet of retail space, as well as a connection between the E and R/W trains, and a glass dome meant to shed light on subway platforms. While the project was expectedly $41 million more than federal government’s allocation of $847 million, requiring riders leaving R/W, 1 or E trains to repay before reaching the 4/5, A/C, J/M/Z and 2/3 trains was not anticipated. The MTA hopes that the Port Authority construction at Ground Zero will scale down some of the project’s costs. Construction will be finished in 2009.
Compromise Reached on Fulton Street Transit Center
Monday, January 08, 2007 | New York Times | Topic: Transportation
New plans for Fulton Street Transit Center include both the desired connector between R/W and E subway lines as well as most of the architecturally desired elements for the new entrance building. Planners have discovered that the connecting tunnel can be built more cheaply than expected by using a portion of the current temporary Path terminal. Plans for a large glass dome over the entrance building have been reduced but not eliminated. Estimated costs of $888 million still exceed the available federal funding of $847 million, but MTA appears to be prepared to meet this shortfall out of their own budget.
Downtown Manhattan Businesses Deal with Hassle of Construction
Sunday, December 24, 2006 | New York Post | Topic: Economic Development
The large number of new projects in downtown Manhattan is having an impact on local businesses, which must deal with the inconveniences of getting around construction work and believe they are seeing lower sales. However supporters believe the new development and infrastructure, including the Freedom Tower and Fulton Street Transit Center, will be a boon to the neighborhood once completed.
Free Underground Transfer Reconfirmed As Part Of Fulton Street Plans
Wednesday, November 29, 2006 | NY1 | Topic: Transportation
With the Fulton Street Transportation Center plans running over budget, there had been discussions of eliminating the platform-to-platform connection between the R/W line at Cortland and E train at World Trade Center. Efforts by MTA board members have led the agency to confirm that it will go ahead with the connection, which will cost $15M to construct. Without the connection, passengers could still transfer underground through the Path station, but would have to swipe again to do so.
Fulton Street Transit Center: Form Challenged by Function
Tuesday, November 28, 2006 | Gothamist | Topic: Urban Design & Architecture
Recent revelations that soaring costs would reduce the size of a magnificent oculus at the planned Fulton Street Transit Center have elicited criticism from board members at the MTA. The fact that any oculus is considered at all angers some, who believe that a platform-to-platform connection between R/W line at Cortlandt Street and the E train at World Trade Center is more important and necessary, however less aesthetically pleasing it is. In the heat of a budget, many push for function above form.
Plans for Fulton Street Transit Hub Adapt to Rising Costs
Monday, November 27, 2006 | NY1 | Topic: Transportation
Due to soaring costs, in particular the rising prices of acquiring buildings on Broadway, the project for a new Fulton Street Transit Hub has been downsized from its original design. MTA officials have reduced the height of the oculus to 20 feet (from 50 feet) and shelved a platform-to-platform connection between the R and W lines at Cortland Street. In order to meet budgetary restrictions the MTA must locate $15 million in new funds to realize the platform connections.
A Weekend Maze
Tuesday, August 22, 2006 | Staten Island Advance | Topic: Transportation
Weekend visits to New York City from Staten Island has become trickier with as many as three transportation projects disrupting normal routes. The building of the Fulton Street Transit Center, the new South Ferry Station, and upgrade of the Wall Street station on the 4 and 5 lines had led to very limited service at night.
Fulton St Delays a Sign of What's to Come?
Wednesday, August 02, 2006 | Metro New York | Topic: Land Use
Attorney Ann Kayman testified to the Supreme Court that the MTA has yet to pay any reimbursement funds to 31 of the 51 businesses they are evicting for the construction of the new Fulton Street stop. Kayman made the case that this foreshadows what will happen to other residents and businesses in a time where eminent domain is behind many of the city’s biggest projects.
Over Budget Means Time to Redesign
Tuesday, May 23, 2006 | New York Times | Topic: Transportation
The opening of the Fulton Street Transit Center has already been delayed since December. Now, due in part to rising real estate, the cost of completing the project has escalated by around $50 million.
Construction to Take Over Downtown
Monday, May 08, 2006 | New York Post | Topic: Economic Development
Lower Manhattan, already buzzing with development, will absorb an immense amount of construction over the next few years, posing unique logistical challenges for both builders and the neighborhood.
Twin Towers Dust Is Nothing to Sneeze At
Tuesday, April 18, 2006 | Other | Topic: Environment
The MTA has decided to postpone a building near the World Trade Center that sits on the site of the planned Fulton Street station due to its possible contamination with toxic dust.
MTA Unable To Provide For Businesses That Will be Displaced
Sunday, April 09, 2006 | Other | Topic: Transportation
Work on the Fulton Street transit center is estimated to displace more than 150 businesses in the area. The MTA is accused of providing ineffective assistance, but the MTA claims that they followed every applicable state and federal law.
MTA Officials Negligent with Fulton Steet Station Project?
Sunday, April 09, 2006 | New York Post | Topic: Transportation
Scott Stringer is demanding a federal probe into possible negligence by state transit officials in connection with the $750million overhaul of the Fulton Street station. The primary allegation is that the MTA and its contractors have not followed the procedures designed to help 160 businesses that rent space in buildings above the station find new offices.
Metro Briefing -- Cortlandt Street Subway Station to Remain Closed And State to Appeal Lawyer's Disqualification In Yards Case
Friday, February 17, 2006 | New York Times | Topic: Economic Development
The Cortlandt Street subway station, closed since August, will likely remain closed due to safety hazards resulting from work on the planned Fulton Street Transit Center.
A New York development agency will appeal Justice Carol R. Edmead's decision to disqualify David Paget as a result of his past work for Forest City Ratner Companies.
Fulton Street Transit Center Completion to be Delayed
Tuesday, October 25, 2005 | New York Newsday | Topic: Transportation
The completion of the planned Fulton Street Transit Center could be delayed up to two years as a result of design and land acquisition delays. Though it might be completed in 2009, it could be functional by 2008.
MTA Plans to Seize Businesses Through Eminent Domain
Friday, October 14, 2005 | Downtown Express | Topic: Transportation
Five small businesses must relocate soon as the MTA plans to take the properties via eminent domain to make room for the Fulton Street Transit Center.
Work underway on Fulton Street Transit Center
Tuesday, August 30, 2005 | The Real Deal | Topic: Transportation
Work has begun on the $750 million Fulton Street Transit Center in lower Manhattan.
Fulton Street Transit Center one year behind schedule
Thursday, May 26, 2005 | New York Daily News | Topic: Transportation
The Fulton Street Transit Center's projected costs have exceeded its $750 million budget. As a result, its glass dome will be scaled back significantly. Plus, the project is a year behind schedule and is not expected to be completed until December 2008.
Design unveiled for new Fulton Street Transit Center
Thursday, May 27, 2004 | Gotham Gazette | Topic: Urban Design & Architecture
This article discusses ths station design, expected public benefits, and the federal financing for the Fulton Street Transit Center.


